A six-project buildout adds near-term solar, dispatchable gas generation, and a 400 MW storage system across Missouri through 2028.
Swipe to explore
This is a map of the six projects in the filing table, not Ameren's complete generation fleet or an assertion that battery MW is equivalent to generation energy output.
Labels and narrative explain the filing. A category marked “arithmetic bridge” or “residual” is calculated from reported totals, rather than a separately reported line.
| Category | Stage | Value | Notes |
|---|---|---|---|
| Solar generation | 1 | 600 | Three projects |
| Natural-gas generation | 1 | 1,600 | Two 800 MW plants |
| Battery storage | 1 | 400 | Big Hollow storage project |
| Disclosed project pipeline | 2 | 2,600 | Six Missouri projects |
| In service during 2026 | 3 | 350 | Bowling Green and Split Rail solar |
| In service during 2027 | 3 | 800 | Castle Bluff gas |
| In service during 2028 | 3 | 1,450 | Gas, battery and solar |
| From | To | Value |
|---|---|---|
| Solar generation | Disclosed project pipeline | 600 |
| Natural-gas generation | Disclosed project pipeline | 1,600 |
| Battery storage | Disclosed project pipeline | 400 |
| Disclosed project pipeline | In service during 2026 | 350 |
| Disclosed project pipeline | In service during 2027 | 800 |
| Disclosed project pipeline | In service during 2028 | 1,450 |